1. The first step is to arrange a site visit. We will meet to discuss your requirements and then prepare a written itemised cost quotation to build your tennis court.
2. A date can be set to commence work and the first job is to prepare the ground where the tennis court will be sited. Safety precautions will be put in place.
3. Once the ground has been prepared we will lay a geotextile membrane over the court area.
4. An MOT Type 1 aggregate sub-base will then be laid over the membrane.
5. A flat 6" x 2" concrete edging will be applied around the periphery of the court.
6. Fencing will be installed around the tennis court.
7. The porous asphalt (tar macadam) surface will then be applied to the court. This will be left to settle for 4-5 weeks.
8. Once the hard surface of the court is ready an application of non-slip coloured paint will be applied. There are a choice of colours:
9. White line marking will then be applied.
10. And finally... GAME ON!!!